Capital Project

  • Warsaw CSD Capital Project: 

    Building A Brighter and Safer Tomorrow For Our Kids!

     

     
     
     
     
     WCSD Tiger Logo
  • Capital Project Update
    June 2020

    Dear Warsaw School Community:

    I wanted to provide a progress update on the Capital Improvement Construction Project for both the Elementary and Middle/High Schools. We are moving full steam ahead with all construction at both schools!

    The following areas have started renovations and upgrades at the Elementary School: Auditorium Theatrical Lighting and Sound System, Gymnasium Bleachers, Kitchen, Cafeteria, the remainder of the Toilet Rooms, Public Address System, and Security Cameras.

    The following areas have started renovations and upgrades at the Middle/High School: Site Work, Fitness Center, Technology Suite, Cafeteria HVAC, Main Gymnasium Floor Refinishing, Locker and Bleacher Replacements, Auditorium Lighting and Sound System, Athletic Storage, Public Address System, and Security Cameras.

    Due to some of the locations of the renovations and upgrades ongoing at the Middle/High School, the Front Parking Lot will be closed for a duration of the Summer so construction work can safely take place. The back parking lot will also be closed in certain locations due to construction work. The parking spaces near the concession stand will remain open.

    All construction areas (both interior and exterior at all buildings) will be sectioned off by fencing, gates, temporary doors and/or walls with proper signage, etc. We ask that everyone stay out of the construction areas for safety concerns.

    Please contact the District Office if you have any questions.

    Matthew Wilkins, Superintendent of Schools

    MHS Front Parking Lot Closure   MHS Back Parking Lot Closure

         


  • Design and Construction Schedule

    May 2017: Vote - Approved!

    June 2017: Schematic Design

    August 2017 (10 months): Design Development

    October 2017 - March 2018: Construction Documents

    March 2018: SED Review (7 months)

    October 2018: SED Approval

    October 2018: Bidding (2 months)

    December 2018: Construction Begins (2 years)