• Warsaw CSD Capital Project: 
    Building A Brighter and Safer Tomorrow For Our Kids!



    Capital Project Update
    January 2021

    Dear Warsaw School Community:

    This is an update on the Capital Improvement Construction Project for both the Elementary and Middle/High Schools. The main Capital Project is completed at all the buildings.

    • The following area has been renovated and turned over for the District’s use at the Middle/High School: new lockers in the main gym locker rooms.
    • The following area has been renovated and turned over for the District’s use at the Elementary School: theatrical lighting and sound system replacements.

    Phase 2 of the project is beginning and includes the replacement of the emergency generators in both buildings. Please contact the District Office if you have any questions.


    Matthew Wilkins, Superintendent of Schools

      
     Weight lifting sets   Weight Room
         


  • Design and Construction Schedule

    May 2017: Vote - Approved!

    June 2017: Schematic Design

    August 2017 (10 months): Design Development

    October 2017 - March 2018: Construction Documents

    March 2018: SED Review (7 months)

    October 2018: SED Approval

    October 2018: Bidding (2 months)

    December 2018: Construction Begins (2 years)